Results

Modification Budget

Type 1/4" Modification Costs ($) 1" Modification Costs ($) 2" Modification Costs ($) 4" Modification Costs ($)
Added Canopy $86,946.10 $86,946.10 $86,946.10 $86,946.10
Permeable Pavement -- -- -- --
New Surface Sinks $11,812.77 $80,544.00 $134,494.80 $303,595.20
Green Roofs -- -- -- --
Underground Storage -- -- -- --
Total $98,758.87 $167,490.10 $221,440.90 $390,541.30